# Steering committee note — Kestrel

**Date:** 12 August 2026

The customer demonstration in week 46 is **important for the relationship but is not a contractual milestone**.

The next **formal decision point is in week 49**. At that point the program must show that all mandatory tests are approved in order to proceed.

Program Management shall return with the consequences of the delivery situation **before any deviation is accepted**.