**From:** Johan Ekelund, Kestrel Programme Manager
**To:** Management
**Date:** 19 August 2026
**Subject:** Delivery situation — my recommendation

We should protect the demonstration in week 46.

My recommendation is to take the express batch and handle the deviation in parallel. A missed
demonstration window will be difficult to explain to the customer.

I propose that we give the supplier a response before week 36.
