# Kestrel program plan — revision D

**Status date:** 20 February 2026
**Prepared by:** Program Office (Erik Nordlander)
**Status:** Superseded by revision E

## Milestones

| Milestone | Week |
|---|---|
| Kestrel unit delivery | 38 |
| Integration window | 43–45 |
| Thermal qualification test | 45 |
| Customer demonstration | 44 |
| Formal decision gate | 49 |

## Change from revision C

The integration window has been shifted by two weeks after rescheduling of rig resources.
Delivery date unchanged.