# Decision note — bounded baseline

**Date:** 4 June 2026
**Decision-maker:** Program owner (Katarina Sjöqvist)
**Decision reference:** PL-2026-06-04-E
**Status:** Approved planning baseline

The program owner adopts **B03, revision E (4 June 2026)** as the planning baseline for its documented milestones: delivery week 42, integration weeks 45–47, thermal test week 47, demonstration week 46, and formal decision point week 49.

The decision applies only to the planning baseline. It does not confirm booked chamber time, completed tests, or deviation acceptance. The Program Office shall follow up on the conditions before the next check-in.