**From:** Tove Ahlgren, Nordvind Systems AB **To:** Procurement, Kestrel program **Cc:** Kestrel program management **Date:** 18 August 2026 **Subject:** Changed delivery schedule for Kestrel unit — IMPORTANT Hello, We need to move regular delivery of the Kestrel unit from week 38 to week 44. The reason is that an unusually small proportion of the units are approved in final inspection. As an alternative, we can deliver a smaller express delivery in week 40. This requires the purchaser to approve a temporary deviation from the quality requirement for surface adhesion (requirement YS-14). The express delivery is sufficient for the first integration test but not for the entire planned series. We need a response regarding the express option no later than week 36 in order to book line time. Kind regards Tove Ahlgren