# Kestrel integration plan **Status date:** 4 June 2026 **Prepared by:** Integration Management ## Test resources The mandatory temperature test is carried out in the large temperature chamber, which in the booking system is called **TK-2**. The test requires **four consecutive days** in the chamber: one day for run-in and stabilization, two days for the sequence itself, and one day for cooling and disassembly. The large TK-2 chamber is the only chamber that can handle the entire test. The reserve chamber, called TK-1, is too small and cannot reach the lowest required temperature. ## Booking Rig time is booked through the Test Department. Booking is done by term and confirmed in the Test Department’s weekly bulletin. ## Conditions - The unit must be delivered and approved in incoming inspection no later than two weeks before test start. - The test cannot be split into stages.