**From:** Johan Ekelund, Kestrel Programme Manager **To:** Management **Date:** 19 August 2026 **Subject:** Delivery situation — my recommendation We should protect the demonstration in week 46. My recommendation is to take the express batch and handle the deviation in parallel. A missed demonstration window will be difficult to explain to the customer. I propose that we give the supplier a response before week 36.