# Kestrel integration plan **Status date:** 4 June 2026 **Prepared by:** Integration Management ## Test resources The mandatory temperature test is performed in the large temperature chamber, called **TK-2** in the booking system. The test requires **four consecutive days** in the chamber: one day for setup and stabilization, two days for the sequence itself, and one day for cooldown and disassembly. The large TK-2 chamber is the only chamber capable of the complete test. The backup chamber, TK-1, is too small and cannot reach the required lowest temperature. ## Booking Rigging time is booked through the Test Department. Bookings are made by term and confirmed in the Test Department's weekly bulletin. ## Conditions - The unit must be delivered and approved in receiving inspection no later than two weeks before the test starts. - The test cannot be split into stages.