PLAN
Kestrel program plan — revision D
English translation of synthetic source B02. Dates, status and uncertainty are preserved. Swedish original
Status date: 20 February 2026
Prepared by: Program Office (Erik Nordlander)
Status: Superseded by revision E
Milestones
| Milestone | Week |
|---|---|
| Kestrel unit delivery | 38 |
| Integration window | 43–45 |
| Thermal qualification test | 45 |
| Customer demonstration | 44 |
| Formal decision gate | 49 |
Change from revision C
The integration window has been shifted by two weeks after rescheduling of rig resources.
Delivery date unchanged.