PLAN
Kestrel program plan — revision E
English translation of synthetic source B03. Dates, status and uncertainty are preserved. Swedish original
Status date: 4 June 2026
Prepared by: Program Office
Status: Current
Milestones
| Milestone | Week |
|---|---|
| Kestrel unit delivery | 42 |
| Integration window | 45–47 |
| Thermal qualification test | 47 |
| Customer demonstration | 46 |
| Formal decision point — the program must show that the requirements are met | 49 |
Change from revision D
Delivery date moved from week 38 to week 42 after rescheduling by the supplier during the
spring. Integration window and test move with it.
Dependencies
The thermal qualification test requires booked time in a thermal chamber according to the integration plan.
Document ID B03 · UTF-8 · 680 bytes