STAFF NEWS

Weekly testing bulletin v24

English translation of synthetic source F05. Dates, status and uncertainty are preserved. Swedish original

Download TXT

From: Test Department

To: Program Office, Integration Management, test users

Date: 12 June 2026

Subject: Weekly testing bulletin v24

Hello everyone,

A brief update from us this week.

Staff. Two new test technicians start in week 34. Introduction takes place as usual.

Calibration. Annual calibration of measuring equipment in hall 2 takes place in week 39. Expect

the hall to be unavailable for two days.

Booking situation in the test hall. The large temperature chamber, known internally as TK-2, is booked

by the Delfin program in weeks 47–48. The booking is confirmed and cannot be moved. The smaller

reserve chamber, TK-1, is out of service for refurbishment through week 50. Other test equipment

is booked as usual through the booking portal.

Forms. A new version of the test-order form is on the intranet. The old one will be removed after summer.

Have a nice weekend!

Test Department