Changed delivery schedule for Kestrel unit — IMPORTANT
English translation of synthetic source A08. Dates, status and uncertainty are preserved. Swedish original
From: Tove Ahlgren, Nordvind Systems AB
To: Procurement, Kestrel program
Cc: Kestrel program management
Date: 18 August 2026
Subject: Changed delivery schedule for Kestrel unit — IMPORTANT
Hello,
We need to move regular delivery of the Kestrel unit from week 38 to week 44.
The reason is that an unusually small proportion of the units are approved in final inspection.
As an alternative, we can deliver a smaller express delivery in week 40. This requires the purchaser
to approve a temporary deviation from the quality requirement for surface adhesion (requirement YS-14). The
express delivery is sufficient for the first integration test but not for the entire planned series.
We need a response regarding the express option no later than week 36 in order to book line time.
Kind regards