Kestrel integration plan

English translation of synthetic source B05. Dates, status and uncertainty are preserved. Swedish original

Download TXT

Status date: 4 June 2026

Prepared by: Integration Management

Test resources

The mandatory temperature test is carried out in the large temperature chamber, which in the

booking system is called TK-2.

The test requires four consecutive days in the chamber: one day for run-in and stabilization,

two days for the sequence itself, and one day for cooling and disassembly.

The large TK-2 chamber is the only chamber that can handle the entire test. The reserve chamber, called

TK-1, is too small and cannot reach the lowest required temperature.

Booking

Rig time is booked through the Test Department. Booking is done by term and confirmed in the

Test Department’s weekly bulletin.

Conditions

The unit must be delivered and approved in incoming inspection no later than two weeks before test start.

The test cannot be split into stages.