Slide 1 — Delivery
A08 states regular delivery week 44. Express option week 40 requires a temporary deviation from YS-14 and is sufficient only for the first integration test.
Slide 2 — Plan
B03 revision E states delivery week 42 and formal decision point week 49. B05 states four consecutive days in TK-2 for the temperature test.
Slide 3 — Next steps
Program Manager’s recommendation: express and parallel deviation handling (D06). For discussion: what supporting material is needed before a decision, and who prepares it?